Erection and prefabrication of piping in pipe bridge in BASF Ludwigshafen

Year: 2017 - 2018
Site: Ludwigshafen, Nemecko
Duration: 7 months
Scope: 2,9 km of SS piping | 2,6 km of CS piping | Primary and secondary supports | Pressure tests

Activities:

  • Planning
  • HSE management
  • Warehouse management
  • Material transport
  • Prefabrication of piping on site
  • Erection of piping
  • Erection of Primary and secondary supports
  • Purging
  • Cleaning of piping including firing with cleaning ball
  • Pressure test
  • Creation of Accompanying Technical Documentation (ATD)
  • Project of final design - AS-BUILT
  • RTG: 10% - 100%
  • Welding method: TIG